why not chem eng logo

whynotchemeng : Graduate

Friday, June 12, 2009

 

Factory Acceptance Test

During the last month I have continued to be heavily involved in the detailed design on a subsea tie-back to produce a gas reservoir back to an existing offshore platform. Part of this project is to supply a Hydraulic Power Unit (HPU).

For those of you who are not too familiar with the workings of hydrocarbon production from a subsea tie-back, the well is drilled and completed on the seabed with a subsea template, manifold and control module. It is these systems that contain all of the master wing valves and subsea safety valves. As these valves lie on the bottom of the seabed they are controlled from the surface by using hydraulic fluids pumped through umbilicals piggy-backed to the production flowline. The fluids are pumped to the subsea control manifold and then turn the valves before being expelled to the sea (don't worry though, these hydraulic fluids meet all the correct environmental regulations and restrictions!).

The HPU is the skid that resides on the platform consisting of all the pumps and hydraulic fluid tanks etc. that supply these valves. This past week I have spent in the subsea vendors factory where the HPU has been fabricated. Prior to offshore installation it is the job all involved parties to send witnesses along to a Factory Acceptance Test (FAT) to ensure that the kit does what it was designed to do and is safe to install on the facility.

The FAT involved: checking all equipment was correctly tagged and installed in the correct orientation etc.; calibrating all level and pressure instrumentation; testing all instrumentation loops; hydrotesting pipes and tubing; ensuring all alarms function correctly and any executive actions (or process trips) correctly execute when mimicing the extremes of operation. All emergency shutdown actions are also tested.

With these checks made and signed-off the equipment is fit to be installed on the platform. Any items that need to be resolved prior to installation that the FAT showed were not acceptable go onto a "PUNCH LIST". The vendor will then action each of these items and will be signed off prior to the equipment being installed.

The next few weeks for me are going to be involved around site installations and commissioning of equipment. When I return I shall post some information on this blog regarding those. Until then.....

Comments: Post a Comment

<< Home

Archives

07/01/2005 - 08/01/2005   08/01/2005 - 09/01/2005   09/01/2005 - 10/01/2005   10/01/2005 - 11/01/2005   11/01/2005 - 12/01/2005   12/01/2005 - 01/01/2006   01/01/2006 - 02/01/2006   02/01/2006 - 03/01/2006   03/01/2006 - 04/01/2006   04/01/2006 - 05/01/2006   05/01/2006 - 06/01/2006   06/01/2006 - 07/01/2006   07/01/2006 - 08/01/2006   08/01/2006 - 09/01/2006   09/01/2006 - 10/01/2006   10/01/2006 - 11/01/2006   11/01/2006 - 12/01/2006   12/01/2006 - 01/01/2007   01/01/2007 - 02/01/2007   02/01/2007 - 03/01/2007   03/01/2007 - 04/01/2007   04/01/2007 - 05/01/2007   05/01/2007 - 06/01/2007   06/01/2007 - 07/01/2007   07/01/2007 - 08/01/2007   08/01/2007 - 09/01/2007   09/01/2007 - 10/01/2007   10/01/2007 - 11/01/2007   11/01/2007 - 12/01/2007   12/01/2007 - 01/01/2008   01/01/2008 - 02/01/2008   02/01/2008 - 03/01/2008   03/01/2008 - 04/01/2008   04/01/2008 - 05/01/2008   05/01/2008 - 06/01/2008   06/01/2008 - 07/01/2008   07/01/2008 - 08/01/2008   09/01/2008 - 10/01/2008   10/01/2008 - 11/01/2008   11/01/2008 - 12/01/2008   12/01/2008 - 01/01/2009   01/01/2009 - 02/01/2009   03/01/2009 - 04/01/2009   04/01/2009 - 05/01/2009   06/01/2009 - 07/01/2009  

This page is powered by Blogger. Isn't yours?